Schmitz Grain

Lake Wilson, MN

Project Description: New Grain Elevator

Summary of Project:

McC Inc was awarded a Design/Build contract from the owner to construct a new grain elevator in Lake Wilson, MN. Our scope of work consisted of structural engineering, contstruction drawings, process design, equipment procurement & installation, spouting, equipment supports & platforms, earthwork, foundations & tunnels, slipform and commissioning. This was the 2nd design/build contract we received from this client.

  • Receiving System rated at 35,000 bph combined
    • One Leg rated at 15,000 bph
    • One Leg rated at 20,000 bph
  • Reclaim System rated at 10,000 bph
  • Concrete Slipform Storage
    • (2) – 195,000 bushel each 52’ dia x 125’ tall
    • (1) – 59,000 bushel wet bin
    • (1) – 47,000 bushel wet bin
  • Dryer System rated at 4,000 bph
  • Load out System rated at 15,000 bph
    • (6) – 2,500 Overhead load out bin